Date

Counting weekdays between two dates

Definition

Counting workdays from a start date through an end date means giving NETWORKDAYS those two dates.

Syntax

=NETWORKDAYS(start_date, end_date)

Arguments

Argument Meaning
start_date The first date of the span. Both ends count as workdays when they fall on a weekday.
end_date The last date of the span. Saturday and Sunday are skipped.

Worked example

A fit-out list stores the start in B2 and the finish in C2.

A: Job B: Start C: Finish
Loft 6 May 2024 10 May 2024
Hall 13 May 2024 17 May 2024
Yard 20 May 2024 22 May 2024

Formula: =NETWORKDAYS(B2,C2)

Result: 5. Monday 6 May through Friday 10 May is five workdays.

Practice

Cell A2 holds the date 4 March 2024. Cell B2 holds the date 15 March 2024. In C2, write a formula that counts the workdays from A2 through B2.

  1. In C2, write a NETWORKDAYS formula that returns the workdays from A2 to B2.
Step 1 of 2
Formulas here use English function names, such as SUM, and a period as the decimal separator, in every language.
Loading the sheet…

Related functions

NETWORKDAYS is the function that counts those workdays and skips weekend days.

Common mistake

Reversing the dates, as in =NETWORKDAYS(C2,B2): the finish is first, so the result is -5 instead of 5.

Related functions

These links are related functions.